21 November 2026 • 6 min read
There is no separate application for the grant. The Ministry of Power's sanction order says projects shall be awarded based on Tariff-Based Competitive Bidding (TBCB) guidelines issued by the Ministry. A developer therefore qualifies by winning a bid, not by applying for a subsidy. 1
The Union Cabinet approved the scheme, and Anurag Thakur said at the briefing that it aims to develop capacity to store excess renewable energy. The selection of BESS developers for VGF grants is carried out through a competitive bidding process involving both public and private sector entities. 4
The operational guidelines say bids are run by a BESS Implementing Agency (BIA), an agency designated by the Ministry of Power for one or more tranches of the scheme. The bid document, called the Request for Selection (RfS), is prepared by the BIA from the scheme guidelines and the BESS TBCB guidelines. 1
Why it matters (our view)
Treat VGF as a tender win, not a grant application: your pricing, land and guarantees decide eligibility.
Read each implementing agency's RfS closely, because the caps, funding source and obligations change from tender to tender.
Plan working capital for the staggered payouts, as most of the grant arrives only after the project is running.
The Ministry of Power sanctioned the scheme to develop 4,000 MWh of BESS capacity. The total outlay is ₹9,400 crores, which includes budgetary support of ₹3,760 crores. It is administered as a Central Sector Scheme. 1
The scheme period is three years, from 2023-24 to 2025-26. Projects falling under the scheme receive approval during this period, and funds will be disbursed up to 2030-31. 1
The sanction order is dated 15th March, 2024 and says the scheme comes into force with immediate effect. The Union Cabinet approved the scheme earlier, on 6 September 2023, according to Akashvani News. 1,6
The central government provides VGF of up to 40% of capital cost for BESS. The sanction order says the VGF is a non-recurring expenditure and is fully funded from central grant. 1
India Briefing describes VGF as meant for projects that have sound economic justification but fall slightly short of full financial viability. It adds that the government generally offers VGF only for infrastructure projects where private sponsors are chosen through competitive bidding. 5
India Briefing reports the scheme targets a Levelized Cost of Storage ranging from INR 5.50-6.60 per kilowatt-hour. The stated aim is to make stored renewable energy a practical option for managing peak power demand. 5
VGF is not paid upfront. The sanction order releases 10% on financial closure, subject to a bank guarantee and the developer holding 90% of the total land required for the project. A further 45% is released on Commercial Operation Date (COD). 1
The remaining 45% is paid in three equal instalments of 15% each, on completion of the 1st, 2nd and 3rd year from COD. The tranches add up to 100%. 1
Projects must be commissioned within 24 months from the date of signing of the Battery Energy Storage Purchase Agreement (BESPA). A bidder should plan its land, bank guarantee and financing around these milestones. 1
| Item | Detail | Source |
|---|---|---|
| Capacity targeted | 4,000 MWh | 1 |
| Total outlay | ₹9,400 crores, incl. ₹3,760 crores budgetary support | 1 |
| VGF ceiling | Up to 40% of capital cost | 1 |
| Approval period | 2023-24 to 2025-26 | 1 |
| Fund disbursal until | 2030-31 | 1 |
| Commissioning deadline | 24 months from BESPA signing | 1 |
| First tranche | 10% on financial closure | 1 |
| Share for Discoms | Minimum 85% of capacity | 6 |
Cabinet briefing coverage says companies availing VGF for setting up BESS must give 85 per cent of the power to distribution companies, and the rest can be shared with other consumers. Akashvani News reports a minimum of 85 percent of BESS project capacity will be made available to Discoms. 4,6
The guidelines assess the system requirement at 572 cycles per year, which the National Load Dispatch Center (NLDC) may increase if required. The NLDC pre-declares stress hours of the grid, typically the evening and morning peaks. 1
The BIA secures discharge during those hours and secures charging power through fixed-term contracts with solar, wind or hybrid sources, plus market purchases. A developer that fails to discharge in the specified hours is liable for a penalty under the BESS TBCB guidelines. 1
The guidelines create a BESS Balancing Pool (BBP) to cover surplus or deficit revenues from BESS projects across all tranches. A BESS Nodal Agency (BNA), designated by the Ministry of Power, oversees the pool. 1
The BIA is paid a trading margin of four paise per kWh of energy sold. If the BIA generates more than 10% surplus revenue annually, it is entitled to an additional three paise per kWh, subject to a cap tied to the surplus. A revenue deficit of more than 10% annually draws a penalty of one paise per kWh. 1
For a startup, this means the buyer is the implementing agency, not the discom directly. The RfS and the BESPA set the commercial terms. 1
For an Indian battery startup, the route to VGF is a tender run by an implementing agency, and later tenders show how it works in practice. SJVN Limited issued a Battery Energy Storage Purchase Agreement for 265 MW/530 MWh in Haryana. It was appointed as Implementing Agency by Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL). The RfS is numbered SJVN/CC-Delhi/REIA/2026/BESS-2 and dated 24.07.2026. 2
That tender combines two funding sources: 250 MW/500 MWh under a VGF scheme supported through the Power System Development Fund (PSDF), and 15 MW/30 MWh under the State Component of the VGF scheme. VGF per developer is limited to Rs. 18,00,000 per MWh, and for the state component, or 30% of the capital cost. 2
The Ministry of Power's June 2025 PSDF scheme provides VGF at Rs. 18 Lakhs per MWh for 30 GWh of BESS capacity, with total support of Rs. 5400 Crores from PSDF. It allocates 25 GWh to 15 States and 5 GWh to NTPC. 3
Other central policy changes help project economics. A June 2025 Ministry of Power order waives ISTS charges at 100% for co-located BESS projects commissioned on or before 30 June, 2028, if the power is consumed outside the state where the project is commissioned. The Ministry has also invited comments on draft amendments to Rule 18 (Energy Storage System) of the Electricity Rules, 2005. 3
India Briefing notes that FDI up to 100 percent is permitted through the automatic route for renewable energy generation and distribution projects, subject to the Electricity Act 2003. Startups with foreign investors should still check the current RfS terms. 5
The scheme provides VGF of up to 40% of capital cost. The grant is non-recurring and fully funded from central grant. 1
In five tranches: 10% on financial closure, 45% on COD, and 15% each at the end of the 1st, 2nd and 3rd year from COD. 1
Through Tariff-Based Competitive Bidding under Ministry of Power guidelines. The BIA prepares the Request for Selection and awards projects. 1
The scheme documents provided here do not state an RTE benchmark. Check the RfS of the specific tender for technical requirements. 1
A minimum of 85 percent of BESS project capacity must be made available to distribution companies, as Akashvani News reports. 6
How this page was made: written with AI from the sources above, read on 21 November 2026. Every figure was checked against the source it cites; lines under "Why it matters" are our view. Editorial standards.