BESS Viability Gap Funding: How Developers Qualify

21 November 2026 • 6 min read

In short

  • Battery storage developers qualify for the VGF scheme by winning a tariff-based competitive bid run by a designated agency, then meeting commissioning, land and bank guarantee conditions.

How a developer qualifies for BESS VGF

There is no separate application for the grant. The Ministry of Power's sanction order says projects shall be awarded based on Tariff-Based Competitive Bidding (TBCB) guidelines issued by the Ministry. A developer therefore qualifies by winning a bid, not by applying for a subsidy. 1

The Union Cabinet approved the scheme, and Anurag Thakur said at the briefing that it aims to develop capacity to store excess renewable energy. The selection of BESS developers for VGF grants is carried out through a competitive bidding process involving both public and private sector entities. 4

The operational guidelines say bids are run by a BESS Implementing Agency (BIA), an agency designated by the Ministry of Power for one or more tranches of the scheme. The bid document, called the Request for Selection (RfS), is prepared by the BIA from the scheme guidelines and the BESS TBCB guidelines. 1

Why it matters (our view)

Treat VGF as a tender win, not a grant application: your pricing, land and guarantees decide eligibility.

Read each implementing agency's RfS closely, because the caps, funding source and obligations change from tender to tender.

Plan working capital for the staggered payouts, as most of the grant arrives only after the project is running.

What the scheme offers: size, outlay and period

The Ministry of Power sanctioned the scheme to develop 4,000 MWh of BESS capacity. The total outlay is ₹9,400 crores, which includes budgetary support of ₹3,760 crores. It is administered as a Central Sector Scheme. 1

The scheme period is three years, from 2023-24 to 2025-26. Projects falling under the scheme receive approval during this period, and funds will be disbursed up to 2030-31. 1

The sanction order is dated 15th March, 2024 and says the scheme comes into force with immediate effect. The Union Cabinet approved the scheme earlier, on 6 September 2023, according to Akashvani News. 1,6

VGF mechanics: up to 40% of capital cost

The central government provides VGF of up to 40% of capital cost for BESS. The sanction order says the VGF is a non-recurring expenditure and is fully funded from central grant. 1

India Briefing describes VGF as meant for projects that have sound economic justification but fall slightly short of full financial viability. It adds that the government generally offers VGF only for infrastructure projects where private sponsors are chosen through competitive bidding. 5

India Briefing reports the scheme targets a Levelized Cost of Storage ranging from INR 5.50-6.60 per kilowatt-hour. The stated aim is to make stored renewable energy a practical option for managing peak power demand. 5

Disbursement in five tranches and bidder conditions

VGF is not paid upfront. The sanction order releases 10% on financial closure, subject to a bank guarantee and the developer holding 90% of the total land required for the project. A further 45% is released on Commercial Operation Date (COD). 1

The remaining 45% is paid in three equal instalments of 15% each, on completion of the 1st, 2nd and 3rd year from COD. The tranches add up to 100%. 1

Projects must be commissioned within 24 months from the date of signing of the Battery Energy Storage Purchase Agreement (BESPA). A bidder should plan its land, bank guarantee and financing around these milestones. 1

BESS VGF scheme at a glance
ItemDetailSource
Capacity targeted4,000 MWh1
Total outlay₹9,400 crores, incl. ₹3,760 crores budgetary support1
VGF ceilingUp to 40% of capital cost1
Approval period2023-24 to 2025-261
Fund disbursal until2030-311
Commissioning deadline24 months from BESPA signing1
First tranche10% on financial closure1
Share for DiscomsMinimum 85% of capacity6

Who buys the power and how the BESS is run

Cabinet briefing coverage says companies availing VGF for setting up BESS must give 85 per cent of the power to distribution companies, and the rest can be shared with other consumers. Akashvani News reports a minimum of 85 percent of BESS project capacity will be made available to Discoms. 4,6

The guidelines assess the system requirement at 572 cycles per year, which the National Load Dispatch Center (NLDC) may increase if required. The NLDC pre-declares stress hours of the grid, typically the evening and morning peaks. 1

The BIA secures discharge during those hours and secures charging power through fixed-term contracts with solar, wind or hybrid sources, plus market purchases. A developer that fails to discharge in the specified hours is liable for a penalty under the BESS TBCB guidelines. 1

The agency layer: BIA, BNA and the balancing pool

The guidelines create a BESS Balancing Pool (BBP) to cover surplus or deficit revenues from BESS projects across all tranches. A BESS Nodal Agency (BNA), designated by the Ministry of Power, oversees the pool. 1

The BIA is paid a trading margin of four paise per kWh of energy sold. If the BIA generates more than 10% surplus revenue annually, it is entitled to an additional three paise per kWh, subject to a cap tied to the surplus. A revenue deficit of more than 10% annually draws a penalty of one paise per kWh. 1

For a startup, this means the buyer is the implementing agency, not the discom directly. The RfS and the BESPA set the commercial terms. 1

What this means for Indian builders

For an Indian battery startup, the route to VGF is a tender run by an implementing agency, and later tenders show how it works in practice. SJVN Limited issued a Battery Energy Storage Purchase Agreement for 265 MW/530 MWh in Haryana. It was appointed as Implementing Agency by Uttar Haryana Bijli Vitran Nigam Limited (UHBVNL). The RfS is numbered SJVN/CC-Delhi/REIA/2026/BESS-2 and dated 24.07.2026. 2

That tender combines two funding sources: 250 MW/500 MWh under a VGF scheme supported through the Power System Development Fund (PSDF), and 15 MW/30 MWh under the State Component of the VGF scheme. VGF per developer is limited to Rs. 18,00,000 per MWh, and for the state component, or 30% of the capital cost. 2

The Ministry of Power's June 2025 PSDF scheme provides VGF at Rs. 18 Lakhs per MWh for 30 GWh of BESS capacity, with total support of Rs. 5400 Crores from PSDF. It allocates 25 GWh to 15 States and 5 GWh to NTPC. 3

Other central policy changes help project economics. A June 2025 Ministry of Power order waives ISTS charges at 100% for co-located BESS projects commissioned on or before 30 June, 2028, if the power is consumed outside the state where the project is commissioned. The Ministry has also invited comments on draft amendments to Rule 18 (Energy Storage System) of the Electricity Rules, 2005. 3

India Briefing notes that FDI up to 100 percent is permitted through the automatic route for renewable energy generation and distribution projects, subject to the Electricity Act 2003. Startups with foreign investors should still check the current RfS terms. 5

Checklist before you bid

  • Read the latest RfS from the implementing agency, since each tender sets its own eligibility, capacity and VGF cap. 2
  • Plan to commission within 24 months of signing the BESPA. 1
  • Line up a bank guarantee and possession of 90% of the required land before financial closure, as the first 10% tranche depends on both. 1
  • Model cash flow around the five tranches, since 45% arrives only at COD and the last 45% over three years. 1
  • Check discharge obligations in the stress hours and the penalty terms in the BESS TBCB guidelines. 1
  • Check the RfS and BESPA for any technical performance requirements, including efficiency, before pricing the bid. 2

Questions people ask

How much VGF can a BESS project get?

The scheme provides VGF of up to 40% of capital cost. The grant is non-recurring and fully funded from central grant. 1

How is VGF paid out?

In five tranches: 10% on financial closure, 45% on COD, and 15% each at the end of the 1st, 2nd and 3rd year from COD. 1

How are developers selected?

Through Tariff-Based Competitive Bidding under Ministry of Power guidelines. The BIA prepares the Request for Selection and awards projects. 1

Does the scheme set a round-trip efficiency benchmark?

The scheme documents provided here do not state an RTE benchmark. Check the RfS of the specific tender for technical requirements. 1

Who gets the power from VGF-backed BESS?

A minimum of 85 percent of BESS project capacity must be made available to distribution companies, as Akashvani News reports. 6

Sources

  1. Ministry of Power, Sanction Order and Operational Guidelines, Scheme for VGF for BESS, 15 March 2024 (primary source, read 21 November 2026)
  2. SJVN Limited, Battery Energy Storage Purchase Agreement for 265 MW/530 MWh (Haryana), RfS dated 24.07.2026 (primary source, read 21 November 2026)
  3. MNRE, Policy & Regulatory Updates, June 2025 (primary source, read 21 November 2026)
  4. Business Today, India rolls out scheme for building robust battery energy storage backbone, 6 September 2023 (primary source, read 21 November 2026)
  5. India Briefing, India Approves Viability Gap Funding Scheme for Battery Energy Storage Systems, 19 September 2023 (primary source, read 21 November 2026)
  6. Akashvani News, Government approves scheme for Viability Gap Funding for development of BESS, 6 September 2023 (report, read 21 November 2026)