21 November 2026 • 7 min read
No single licence covers a commercial earth station in India. The sources show three separate approvals. The Wireless Planning and Coordination (WPC) Wing of the Department of Telecommunications (DoT) issues the radio licence. The SACFA process clears the physical site. IN-SPACe authorises certain space-related ground facilities under the Indian Space Policy 2023. 2,3,4
Which of these you need depends on what the station does. A teleport that uplinks TV channels follows one WPC route. A telemetry and telecommand network follows another. A gateway that links satellites to terrestrial networks is the subject of a TRAI recommendation made in 2022. 1,2,7
Why it matters (our view)
Treat the three approvals as one project plan, because a delay at the WPC decision letter or the SACFA stage holds up the licence itself.
Watch the gateway framework and the royalty position closely, since they decide the cost of running a constellation ground network in India.
Confirm the current application route with DoT and IN-SPACe before you commit equipment orders.
The DoT eServices portal describes two WPC licences for earth stations. The teleport licence is for an earth station facility from where multiple TV channels carrying audio, video and content can be uplinked to a geostationary satellite on a permitted frequency band. The telemetry and telecommand licence is for owning and operating a satellite-based Telemetry and Telecommand Network. 2,7
Eligibility differs. For a teleport, the portal says any Indian entity having valid permission from MIB can apply. For the telemetry and telecommand network, it says an Indian entity holding valid transponder allocation can apply. 2,7
Both pages list a similar document set: link budget calculations, carrier plan details, transponder allocation and an RF chain diagram. The teleport page adds a copy of MIB permission and a schematic diagram. The telemetry page asks for PAN Card/CIN. 2,7
The DoT portal lists the same five steps for both licences. Submit the application on the Saral Sanchar portal. Upload the signed application with all required documents. The WPC Wing scrutinises it. Then pay the applicable fees, download the decision letter, and proceed with equipment procurement and SACFA clearance. The licence is downloaded only after that step is complete. 2,7
This order matters. SACFA clearance comes after the decision letter and before the licence is issued, so it sits inside the WPC process rather than after it. Validity is one year to five years at a time, according to the portal. 2,7
A notice on both pages says new applications under the Indian Telegraph Act 1885 have stopped being accepted for Unified Licences, Standalone Licences, registrations and permissions. Applicants are directed to the Authorisation Portal from 25.06.2026 onwards, for new grants under the Telecommunications Act, 2023 or for migration of existing licences. 2,7
The DoT portal says SACFA clearance is mandatory for setting up wireless communication infrastructure, including telecom towers, base transceiver stations and radio antennas. It is issued by the WPC Wing. It checks frequency allocation compliance and aviation safety, including height limits set by the Ministry of Civil Aviation. 3
There are four categories. Mast Height has a VSAT sub-category for very small aperture terminal earth stations. Full Siting involves inter-agency coordination with defence and aviation authorities and, per the portal, is used for satellite uplink stations, large broadcasting stations and sites near airports or military installations. Exemption covers low-risk setups such as indoor Wi-Fi. Additional Antenna covers new antennas on an already cleared site. 3
The portal lists the documents: antenna and structure heights, latitude and longitude, site map, Google Earth image, frequency details, an undertaking on interference and EMF norms, equipment details, and a frequency assignment letter. An AAI height clearance certificate is needed near airports or above certain heights. 3
The portal states the standard processing fees: INR 1,000 per application for general SACFA applications, INR 100 per additional antenna, and INR 100 per small cell on street furniture. Applications go through the Saral Sanchar portal: submit, upload documents, pay, then download the certificate. 3
Validity is listed as lifetime unless revoked by a SACFA member. The page also lists circulars from 2021 and 2022 on simplifying the SACFA process for towers, which shows the process has been revised recently. 3
The Indian Space Policy 2023 makes IN-SPACe the single window agency for authorising space activities by government entities and non-government entities. Among the activities it lists are the establishment and operation of TT&C Earth Stations, and of Satellite Control Centres and satellite data reception stations. 4
The policy defines a TT&C Earth Station as an earth station for receiving telemetry from, tracking and command of a Space Object. It encourages non-government entities to establish and operate such ground facilities. It also encourages them to offer national and international satellite communication services using owned, procured or leased GSO or NGSO satellites. 4
IN-SPACe's May 2024 Norms, Guidelines and Procedures document has a chapter on establishment and operation of ground systems, and application templates for each authorisation category. The excerpt provided does not reproduce those requirements, so check the full document before applying. 5
If you plan a teleport, check your MIB permission first, because the WPC teleport page lists it as the eligibility condition and as a required document. If you plan a telemetry and telecommand network, you need a valid transponder allocation before you apply. Neither can be fixed after the fact. 2,7
If you plan a gateway for a satellite constellation, the licensing position is still shaped by TRAI's recommendation of 29th November 2022, made on a DoT reference dated 10.09.2021. The DoT reference notes that the licence conditions at the time required a service licensee to establish its own gateway, and that narrow beams from LEO and MEO satellites may need multiple gateways. DoT asked TRAI to recommend a framework covering licence fee, entry fee, bank guarantee and NOCC charges. 1
Inmarsat India's comments to TRAI, dated 20 December 2021, show what industry asked for. It supported a separate gateway earth station licence category covering fixed-location gateways, with SACFA clearance, certification by TEC-DoT and NOCC-DoT performance testing. It also said the carrier frequency assignment should go to the service licensee. These are Inmarsat's views, not rules. 8
On spectrum cost, Inmarsat said the WPC formula involving the royalty could lead to potentially exorbitant fees for high throughput satellites and new NGSO constellations. The sources provided do not give the royalty formula, so budget for it only after getting figures from WPC. 8
Since the Telecommunications Act, 2023 now governs new authorisations, confirm on the Authorisation Portal which route applies to your facility before you file. 2
| Approval | Issued by | What it covers | Source |
|---|---|---|---|
| WPC teleport licence | WPC Wing, DoT | Uplink of TV channels to a geostationary satellite | 2 |
| WPC telemetry and telecommand licence | WPC Wing, DoT | Satellite-based telemetry and telecommand network | 7 |
| SACFA clearance | WPC Wing, DoT | Siting, frequency and aviation safety checks | 3 |
| SACFA general application fee | DoT portal | INR 1,000 per application | 3 |
| Authorisation of TT&C Earth Stations | IN-SPACe | Establishment and operation of TT&C Earth Stations | 4 |
| Gateway licensing framework | DoT, on TRAI recommendation | Recommendation dated 29th November 2022 | 1 |
The table below sets out each approval, who issues it and what the sources say about it. It is a reading aid, not legal advice. 2,3,4
The DoT portal says SACFA clearance is mandatory for wireless communication infrastructure such as radio antennas. It lists a VSAT mast height category and says Full Siting is used for satellite uplink stations. 3
The Indian Space Policy 2023 says IN-SPACe authorises the establishment and operation of TT&C Earth Stations, Satellite Control Centres and satellite data reception stations. 4
The DoT portal says any Indian entity having valid permission from MIB can apply. Validity is one year to five years at a time. 2
DoT asked TRAI in 2021 for a licensing framework for satellite earth station gateways, and TRAI issued recommendations on 29th November 2022. Inmarsat India supported a separate gateway licence category in its comments. 1,8
The DoT portal says new applications under the Indian Telegraph Act 1885 have stopped being accepted for the listed licence types. It directs applicants to the Authorisation Portal from 25.06.2026 onwards. 2
How this page was made: written with AI from the sources above, read on 21 November 2026. Every figure was checked against the source it cites; lines under "Why it matters" are our view. Editorial standards.