National Green Hydrogen Mission: SIGHT and what startups can apply for

1 November 2026 • 5 min read

In short

  • SIGHT (₹17,490 crore to 2029-30) pays bid winners among electrolyser makers and hydrogen producers; startups can seek up to ₹5 crore per project from a ₹100 crore call (PIB 2025).

A Mission with a ₹19,744 crore outlay looks like a pot a seed-stage company can tap. Most of that money is not set up that way. The big incentive programme, SIGHT, is a bidding scheme for factories and plants. A startup's openings are narrower and sit in other parts of the Mission. This page separates the two, using PIB releases, the SECI bid documents and a law-firm note on the guidelines.

1. How the Mission's money is split

The Union Cabinet approved the National Green Hydrogen Mission on 4 January 2023. PIB gave the initial outlay as ₹19,744 crore, divided as follows.

PartOutlayWhat it funds
SIGHT programme₹17,490 croreIncentives for making electrolysers in India and for producing green hydrogen
Pilot projects₹1,466 croreTrials in new end-use sectors and production routes
R&D₹400 croreResearch projects, including the public-private SHIP partnership
Other components₹388 croreEnabling work such as standards and skills

A PIB note of November 2025 says the outlay runs until financial year 2029-30. It also puts the 2030 targets at 5 million metric tonnes a year of green hydrogen production capacity, backed by about 125 GW of new renewable energy.

2. SIGHT for electrolyser makers

SIGHT's first part rewards companies that set up electrolyser factories in India. A Khaitan & Co note of 12 August 2024 summarises the rules, which MNRE issued in letters dated 28 June 2023 and 16 March 2024. The Solar Energy Corporation of India (SECI) runs the bids.

  • Incentive: paid on manufacturing capacity, falling each year, for five years.
  • How winners are picked: bidders are scored on the specific energy consumption of the electrolyser and on local value addition.
  • Capacity on offer: 1,500 MW in each of Tranche I and Tranche II. Tranche I had 1,200 MW for any stack technology and 300 MW for stacks developed in India. Tranche II had 1,100 MW, 300 MW and a further 100 MW for smaller units built on India-developed stacks.
  • Eligibility: based on the bidder's net worth per MW of capacity it bids for, with different thresholds in each tranche.
  • Cap per company: SECI's amendment to the Tranche II bid document limits a bidder and its group companies to 300 MW across all tranches and buckets.

Khaitan notes that the lower net worth threshold in Tranche II "paves the way for smaller manufacturing entities and nascent start-ups". The sources I opened do not give the threshold figures. If you make electrolyser stacks, read the current SECI bid document before you plan.

3. SIGHT for hydrogen producers

The second part pays for green hydrogen production, and PIB describes companies being allocated annual production capacity. PIB reports that as of May 2025, 19 companies had been allocated 862,000 tonnes a year of green hydrogen production capacity and 15 firms had been awarded 3,000 MW a year of electrolyser manufacturing capacity. I could not open the production-incentive guidelines, so I do not give their rates or bid rules here.

A rule that applies to anyone who takes an incentive: under the Green Hydrogen Certification Scheme of India, launched in April 2025, a Final Certificate is mandatory for a production facility that receives central or state subsidies or incentives, or that sells or uses the hydrogen in India. Hydrogen counts as green if emissions are not more than 2 kg of CO2 equivalent per 1 kg of hydrogen. The Bureau of Energy Efficiency accredits the certifying agencies.

4. What a startup can apply for

RouteFit for a startupDetail
Start-up call for proposalsDirectPIB says a ₹100 crore call supports start-ups working on hydrogen production, storage, transport and use, with funding of up to ₹5 crore per project
R&D scheme and SHIPDirect or in a consortiumThe ₹400 crore R&D scheme was already funding 23 projects by November 2025; a second round opened in July 2025
SIGHT electrolyser bidOnly with a stack and net worth to matchSmaller-unit bucket in Tranche II; net worth test applies
SIGHT production bidUnlikely for most startups (our reading)Allocations so far went to companies building production capacity
Pilot projectsUsually as a technology partnerExamples in PIB: steel, mobility and shipping pilots

On the start-up call, a trade report dated 16 September 2025 says the National Institute of Solar Energy (NISE) issued the call and that each start-up can receive up to ₹5 crore or 80% of equipment costs, whichever is lower. That is a secondary source. I could not confirm whether the call is still open or find the eligibility rules, so check the NISE and Mission portals before you plan around it.

5. Before you apply

  • [ ] Decide which route you are: electrolyser maker, hydrogen user or producer, or technology startup.
  • [ ] For SIGHT bids, read the latest SECI bid document and the MNRE guidelines, and test your net worth against the per-MW threshold.
  • [ ] For the start-up call or R&D rounds, check the NISE and Mission portals for open dates, eligibility and the funding formula.
  • [ ] Plan for the Green Hydrogen Certification Scheme if any hydrogen you make will be sold in India or supported by an incentive.
  • [ ] Keep a record of the specific energy consumption and local value addition of your design, because the electrolyser bids score both.

These schemes change by tranche and call, so confirm current terms with MNRE or SECI before you commit capital.

Questions people ask

Can a startup apply for SIGHT?

Yes in principle, in the electrolyser manufacturing part, if it meets the net worth test for the capacity it bids for. Tranche II added a bucket for smaller units and a lower threshold. Most startups will find the start-up call or the R&D scheme a better fit.

How big is the SIGHT budget?

₹17,490 crore of the Mission's ₹19,744 crore outlay, running to financial year 2029-30.

What is the ₹100 crore call for start-ups?

A call for proposals for start-ups working on hydrogen production, storage, transport and utilisation, with funding of up to ₹5 crore per project, according to PIB in November 2025. Check the portals for whether it is open now.

Do I need certification for the hydrogen I make?

If your facility receives subsidies or incentives from the central or state governments, or sells or uses the hydrogen in India, a Final Certificate under the Green Hydrogen Certification Scheme is mandatory.

Sources

  1. PIB, Cabinet approves National Green Hydrogen Mission, 4 January 2023
  2. PIB, Unlocking India's Green Hydrogen Production Potential, 12 November 2025
  3. Khaitan & Co, Understanding the Scheme Guidelines for Implementation of the SIGHT Programme Component I, 12 August 2024
  4. SECI, Amendment 01 to the Tranche II electrolyser manufacturing bid document
  5. OmniCore, NISE issues CfP for pilot projects from start-ups developing innovative green hydrogen, 16 September 2025